BOILER MODULE DELIVERY
We have marked a new breakthrough in manufacturing of the first boiler module for a European client.
This huge boiler module/skid (10 x 5 x 7m) is manufactured in accordance with ABS MODU RULES.
Such tight schedule (4 months) with various categories of works from material procurement, mechanical fabrication of non-standard 2mm wall thickness, coating, insulation, inspection, test, transportation & delivery… utilized our best resources to keep up with client & end-user’s requirement.
Installation of fuel oil, steam (main), CO2 piping and electrical system is one of the most challenging pack in which space of the module limits.
All involved parties are entirely satisfied with the project team’s performance, cooperation and attitudes.
The success of this delivery has not only gained us the trust from the parties but also opened a wide path for such equipment business in the future.