PROGRESS UPDATE FOR NPK FERTILIZER PLANT CONSTRUCTION PROJECT


This new NPK plant in Vietnam is expected to meet 80% of fertilizer demand in the country’s agriculture. 

Being one of our major jobs in 2017, this NPK fertilizer project progresses at 51% on schedule with many major items was successfully installed such as Dryer Drum, Cooling Drum, Granulation Drum, Coating Drum, Conveyor system and other miscellaneous items.

Cramped construction site is causing many challenges for the project team. The client has expressed its satisfaction with AlphaECC’s performance.