Dong Xuyen Industrial Zone, Rach Dua Ward, Vung Tau City, S.R. Vietnam
info@alpha-ecc.com






Acid Pipeline for Baconco Fertilizer


Baconco has just granted the Letter of Intent to AlphaECC to perform the new construction for the Acid Pipelines inside the factory.

The pipelines length is about 1,000m, from Baria Sereze Port to the factory tank farm. It is on and underground.

AlphaECC scope of work will be:

  • Demolition of the existing pipelines including cleaning of residual acid agents inside the line.
  • Engineering design of new pipelines
  • Procurements
  • Installation
  • Commissioning and start-up.

The work shall be started by early of September