MODIFICATION OF PROCESS PIPING AND SUPPORT STRUCTURE ON DGCP PLATFORM COMPLETED
In August, our offshore team completed the repair modification of old process piping support and replacement of support structure on DGCP offshore platform. It took the project team only two weeks for the preparation, scaffolding work, onshore fabrication, offshore installation, leak test, purging, commissioning. Total thirteen men were mobilized for the offshore work. The tight schedule, strict safety and quality requirements were all met to the appreciation from our client.