Dong Xuyen Industrial Zone, Rach Dua Ward, Vung Tau City, S.R. Vietnam
info@alpha-ecc.com

BP Namconson Phase II, Dinhco Gas Processing Plant Expansion Project


Today 26.11.2007, ALPHA ECC has officially signed the contract with BP for the implementation of Structural, Machanical and Piping package, a major part of BP Dinhco Expansion Project.

BP is the main operator of the Nam Con Son gas to power development located in the BaRia - Vung Tau Province of South Vietnam. The development is based on the Lan Tay and Lan Do gas fields. Gas is delivered via a 377km pipeline to an onshore terminal for processing prior to onward transmission to a power station.

The new expansion will be perform in parallel with the existing on-going terminal, without shutting down the terminal, that requires an utmost attentions and cares for the safety. All the site hotworks will be performed under Positive Pressure Habitat.

 