BP Namconson Phase II, Dinhco Gas Processing Plant Expansion Project
Today 26.11.2007, ALPHA ECC has officially signed the contract with BP for the implementation of Structural, Machanical and Piping package, a major part of BP Dinhco Expansion Project.
BP is the main operator of the Nam Con Son gas to power development located in the BaRia - Vung Tau Province of South Vietnam. The development is based on the Lan Tay and Lan Do gas fields. Gas is delivered via a 377km pipeline to an onshore terminal for processing prior to onward transmission to a power station.
The new expansion will be perform in parallel with the existing on-going terminal, without shutting down the terminal, that requires an utmost attentions and cares for the safety. All the site hotworks will be performed under Positive Pressure Habitat.